Zur Effizienz von Schieneninfrastrukturbau-vorhaben am Beispiel des Brenner-Basistunnels.Die Zukunft der Schiene mit Milliardeninvestitionen verbaut?

Kummer, Sebastian and Nagl, Philipp and Schlaak, Jan-Philipp (2006) Zur Effizienz von Schieneninfrastrukturbau-vorhaben am Beispiel des Brenner-Basistunnels.Die Zukunft der Schiene mit Milliardeninvestitionen verbaut? Institut für Transportwirtschaft und Logistik, WU Wien.

[img]
Preview
PDF
forschungsbericht_schieneninfrastruktur_1-2006_v1-3.pdf

Download (500kB)

Abstract

Cost overrun has become a major issue regarding infrastructure projects. Especially in regard to railway infrastructure and the construction of tunnels, building costs are regularly exceeding the original estimates. This article discusses the reasons for this apparently common fact. In addition, reasons for and consequences of misassigned infrastructure investments are pointed out and a concept called "lifetime-based infrastructure controlling" to improve the efficiency of infrastructure projects is outlined. To highlight the importance of this field of research the serious consequences of wrong investments in infrastructure are shown by discussing the current "Brenner-Basistunnel"-project in Austria. (author's abstract)

Item Type: Other
Additional Information: Forschungsbericht 1/2006 (Überarbeitet Version 1-3)
Divisions: Departments > Welthandel > Transportwirtschaft und Logistik > Kummer
Depositing User: Dissertation Administrator
Date Deposited: 27 Sep 2011 08:30
Last Modified: 11 May 2015 15:16
Related URLs:
FIDES Link: https://bach.wu.ac.at/d/research/results/54969/
URI: https://epub.wu.ac.at/id/eprint/3227

Actions

View Item View Item

Downloads

Downloads per month over past year

View more statistics